Quaterly Compliances Under RERA – Bashmakh & CO

MahaRERA shall implement "Financial Quarter Based Project Progress Reporting System" for all MahaRERA registered real estate projects. Promoters shall file Quarterly Progress Reports (QPR) as per Financial Quarters within 7 days of the Quarter End (Due Dates will be every 7th day of July, October, January and April respectively). The first financial quarter based QPR will be due to be filled by 15th August, 2021 for all registered projects (for April May June Quarter) irrespective of the date of their last QPR filled.